Q:

Why not wait an additional 30 days before acquiring the land for the plant?

2
Like
Answer
Comment
Flag
Thanks for your feedback!
A:

1 Answer

rank
1
2
Like
Comment
Flag
As the lead agency, the Town of Cary has a legal obligation to keep this project on track in order to meet the State’s mandate of having the plant operational by January 2011. The schedule is already so compressed that two processes -- design, which depends on land acquisition, and permitting must occur at the same time. Now that all of the Partners have agreed to the preferred site, Cary must move forward the design process in the form of land acquisition. Specifically, an additional 30 days’ delay affects the following sequence of activities, which are scheduled to be completed in full by December 2006: Selecting an engineering design firm for final design Initiating site and control surveys for preparation of site development plans and specifications > Preparing site development plans and specifications (access road; site utility roads; utility installation [water, electric, communications]; rough grading; sedimentation and erosion control; site-access control) The other process, ...  more
westernwakepartners.org

Related Videos

Add your answer...

Top Answerers

1.
Bonnie Williamson
17 Answers in the past week
2.
rene essme
5 Answers in the past week
3.
micheal l
4 Answers in the past week

Top Askers

1.
wu ting
2 Questions in the past week
2.
John Montgomery
1 Question in the past week
3.
surina vargas
1 Question in the past week

Top Supporters

1.
Bonnie Williamson
12 Likes given in the past week
2.
Andrew Zenger
12 Likes given in the past week
3.
micheal l
1 Like given in the past week
...